The Co-op team (Wayne S, Craig, Clint & John) held a meeting on Thursday 03 August with Wayne Arndell (road contractor), Ian Slapp and Justin Chapman (AS Engineering) regarding our Nevertire Road Stage 1 Construction Tender.
The meeting went well, with our Engineers walking through the contract in detail to ensure Wayne Arndell was aware of all requirements and to obtain further clarification on costs.
Wayne Arndell was confident that he could complete the project. His start date should be mid October, depending on progress of his current commitments and our job would take approximately two weeks.
He was also interested in providing other road services and consider future works on stage 2.
AS Engineering will prepare the contract for signing once some minor details are sorted with Wayne A.
In the meantime we will start on some of our actions including:
- Notify neighbours on Nevertire of schedule/timing of roadworks
- Notify Goolawah Community when construction begins to use Illa Langi Road instead of Nevertire.
Cooperative members are reminded that all liaison with contractors and road workers is via the NT Stage 1 Road Committee. If you have any issues please bring these directly to the liaison team (Wayne Skinner and Craig Singleman), do not discuss with the workers on site.
Good news is that Council has removed the requirement for a bond and reduced the road maintenance period to 6 months. Revised s138 approval is attached below.
Any questions please feel free to speak to a member of the board or NT Stage 1 road committee.
(Board of Directors)
KSC RA2300263 Stage 1 Section 138 Approval – Nevertire Rd_Illa Langi Road
Construction work will be on Nevertire Road in October not Illa Langi. Please ensure contact with our contractors during this period is only via the liaison team Craig Singleman and Wayne Skinner. Thank you
There will be many problems with illalangi by the time october comes ,it has been graded flat by some incompadent operator , needs urgent attention or it will deterioarte very fast ,
The roads i shaped and finished here 15 years ago still have no potholes ,yet the idiots we hire can’t make them last a year ,it is pathetic. and we pay these idiots ,